JT Brack logoTotal Funds
$11,966,712

Total Spend to date
$4,215,369

Architect: Chesney/Morales
Contractor: Morganti/Casias
Project Status: Construction

What is unique to this project is the age of the campus and the minimal upgrades it has received throughout the years. Architects and staff discussed relocating library to the 1st floor and the renovations to classrooms. Like other schools we also discussed a new main entry to ensure the safety to our students.

Renovations and upgrades to include:

  • Classroom spaces (general learning, science, art, music, special education)
  • Restrooms
  • Cafeteria/kitchen
  • Stage
  • Library
  • Heating, ventilation and air conditioning
  • Plumbing and electrical
  • Technology infrastructure for new and renovated spaces
  • Lighting
  • Fire sprinkler systems
  • Special needs accessibility in entryways, restrooms, and other areas
  • Front-entry modifications to improve security
  • Roofing, building exterior and site improvements
     

Latest Updates

May 2020: The new main entry and drop off canopy has been completed.

Workers are completing the Phase 3 classroom area and new library. Scheduled to be done by the end of May 2020.

Demolition and abatement has begun on the Cafeteria Dining Area so it can be ready for the start of the fall semester. The kitchen is still being used to serve meals in support of the COVID-19 efforts and therefore construction cannot begin on it just yet.

The classrooms in the Phase 4 Area upstairs are being emptied, and workers should start demolition and abatement in that area mid-May so it can be ready for use at the start of the fall semester.

The second chiller has arrived on site, and is currently being piped in.

Weekly construction meetings are taking place on Wednesdays at 10:30 a.m. in the construction trailer on site.

4.16.19: Stakeholder Meeting. Click here for the presentation.

9.20.18: A Community Meeting took place in the Cafeteria. Click here for the presentation.

3.22.18: A Project Advisory Team meeting was held. Chesney/Morales Architects met with school leaders, faculty and several members from the community.

JT Brackenridge ES Summary Bond Expenditures
Budget Description Budget Committed Costs Cost to Date Uncommitted Costs
Construction $8,975,034 $8,883,943 $3,501,056 $91,091
Soft Costs $1,914,674 $1,172,375 $714,313 $742,299
FFE $359,001 $359,001
Technology $119,667 $136,669 $0
Contingency $403,877 $17,002 $386,875
Project Total $11,722,253 $10,209,989 $4,215,369 $1,579,266


Legend:

Construction:  New construction and renovation costs, contractor and design contingency
Soft Costs:  Architect design fees, Construction Manager fees, Design Consultants, QA/QC Services, fees, temporary facilities, abatement
Furniture, Fixtures & Equipment (FFE):  Classroom furniture, owner provided equipment
Technology:  Technology hardware & infrastructure
Contingency:  Owner's contingency, inflation, project reserves




  • Category
    School Year
    Vendor Name
    Total Expenditures
    Construction
    2018-2019
    MORGANTI TEXAS/CASIAS JOINT VE
    $319,485.20
    Construction
    2018-2019
    SAFEWAY SUPPLY, INC.
    $1,888.60
    Construction
    2019-2020
    MORGANTI TEXAS/CASIAS JOINT VE
    $2,856,181.40
    Soft Costs
    2017-2018
    CHESNEY MORALES PARTNERS, INC.
    $102,632.32
    Soft Costs
    2017-2018
    PROTECTION DEVELOPMENT, INC.
    $375.00
    Soft Costs
    2018-2019
    ALPHA TESTING INC.
    $4,100.00
    Soft Costs
    2018-2019
    CALDERON UNDERGROUND UTILITIES
    $8,550.00
    Soft Costs
    2018-2019
    CHESNEY MORALES PARTNERS, INC.
    $365,831.36
    Soft Costs
    2018-2019
    FASTSERV SUPPLY, INC.
    $37.00
    Soft Costs
    2018-2019
    GULF COAST PAPER CO INC
    $1,129.60
    Soft Costs
    2018-2019
    IRON LOCK CONSTRUCTION SVC LLC
    $355,380.55
    Soft Costs
    2018-2019
    KFW SURVEYING
    $9,900.00
    Soft Costs
    2018-2019
    MCGRATH RENTCORP
    $82,800.00
    Soft Costs
    2018-2019
    MISSION RESTAURANT SUPPLY CO.
    $4,220.00
    Soft Costs
    2018-2019
    TEXAS LOCK & DOOR CLOSER INC.
    $504.00
    Soft Costs
    2018-2019
    TTL, INC.
    $7,535.00
    Soft Costs
    2018-2019
    VALLA CONSTRUCTION, INC
    $17,701.26
    Soft Costs
    2019-2020
    B & M LIMITED PARTNERSHIP
    $4,270.91
    Soft Costs
    2019-2020
    CHESNEY MORALES PARTNERS, INC.
    $62,961.00
    Soft Costs
    2019-2020
    MCGRATH RENTCORP
    $31,237.50
    Soft Costs
    2019-2020
    TTL, INC.
    $26,819.24
    Technology
    2019-2020
    PIRAINO CONSULTING, INC.
    $116,344.10
    Page 1 of 1