  • Lanier High School Kitchen

  • Lanier High School 2nd Floor Classrooms

  • Lanier High School

  • Lanier High School Cafeteria

  • Lanier High School Main Area

  • Lanier High School South Side Cutout

 

Total Funds
$46,894,508

Total Spend to date
$12,965,586

Architect: LPA, Inc.
Contractor: Gilbane
Project Status: Construction

Renovating the main building at Lanier HS will be challenging due to its historic auditorium and lack of windows in the building. The design team is reviewing the current Bond project scope, and is looking at a previous programming survey to provide an overview of the current building design process.

Renovations and upgrades to include:

  • Classroom spaces (general learning, science, fine arts, special education)
  • Restrooms
  • Cafeteria/kitchen
  • Auditorium
  • Heating, ventilation and air conditioning
  • Plumbing and electrical
  • Technology infrastructure for new and renovated spaces
  • Lighting
  • Fire sprinkler systems
  • Special needs accessibility in entryways, restrooms, and other areas
  • Front-entry modifications to improve security
  • Athletic track re-coating
  • Roofing, building exterior and site improvements

Latest Updates

05.11.19: Community Open House held for members of the community to get a glimpse of the construction that will update Lanier High School, while taking time to view the campus many folks remember. The open house featured awards that students have won throughout the years, tours of the classrooms, a discussion on the Bond project, remarks from campus and District leaders, a historical lookback at Lanier, and fine arts displays including live musical performances and artwork.

4.10.19: Stakeholder Meeting. Click here for the presentation.

9.25.18: A Community Meeting took place in the Library. Click here for the presentation.

8.30.18: Lanier High School Mural Location meeting. Presentation is here.

4.19.18: A Project Advisory Team Meeting was held.

Lanier HS Summary Bond Expenditures
Budget Description Budget Committed Costs Cost to Date Uncommitted Costs
Construction $35,170,881 $35,170,881 $10,681,910 $0
Soft Costs $7,503,121 $3,328,616 $2,283,676 $4,174,505
FFE $1,406,835 $1,406,835
Technology $468,945 $468,945
Contingency $1,582,689 $1,582,689
Project Total $46,132,472 $39,261,533 $12,965,586 $7,632,975


Legend:

Construction:  New construction and renovation costs, contractor and design contingency
Soft Costs:  Architect design fees, Construction Manager fees, Design Consultants, QA/QC Services, fees, temporary facilities, abatement
Furniture, Fixtures & Equipment (FFE):  Classroom furniture, owner provided equipment
Technology:  Technology hardware & infrastructure
Contingency:  Owner's contingency, inflation, project reserves




  • Category
    School Year
    Vendor Name
    Total Expenditures
    Construction
    2018-2019
    GILBANE BUILDING COMPANY
    $58,172.95
    Construction
    2018-2019
    LA LANNE, MARY C.
    $3,483.00
    Construction
    2019-2020
    ALVARADO, JUAN M.
    $2,176.00
    Construction
    2019-2020
    GILBANE BUILDING COMPANY
    $7,070,536.00
    Soft Costs
    2017-2018
    LPA, INC.
    $395,302.77
    Soft Costs
    2018-2019
    GULF COAST PAPER CO INC
    $1,265.40
    Soft Costs
    2018-2019
    INDUSTRY1ONE STAFFING
    $3,509.82
    Soft Costs
    2018-2019
    LPA, INC.
    $976,273.44
    Soft Costs
    2018-2019
    MCGRATH RENTCORP
    $707,758.80
    Soft Costs
    2018-2019
    MISSION RESTAURANT SUPPLY CO.
    $4,220.02
    Soft Costs
    2018-2019
    PRESIDIO NETWK. SOLUTIONS INC.
    $5,265.50
    Soft Costs
    2018-2019
    RABA-KISTNER CONSULTANTS, INC.
    $2,332.50
    Soft Costs
    2018-2019
    TERRACON CONSULTANTS, INC.
    $12,695.75
    Soft Costs
    2018-2019
    TEXAS LOCK & DOOR CLOSER INC.
    $806.40
    Soft Costs
    2018-2019
    VALLA CONSTRUCTION, INC
    $89,402.02
    Soft Costs
    2018-2019
    VICKREY & ASSOCIATES INC
    $23,993.49
    Soft Costs
    2019-2020
    B & M LIMITED PARTNERSHIP
    $8,802.24
    Soft Costs
    2019-2020
    GILBANE BUILDING COMPANY
    $59,657.47
    Soft Costs
    2019-2020
    GULF COAST PAPER CO INC
    $417.72
    Soft Costs
    2019-2020
    LPA, INC.
    $210,559.47
    Soft Costs
    2019-2020
    MCGRATH RENTCORP
    $61,540.49
    Soft Costs
    2019-2020
    PIRAINO CONSULTING, INC.
    $4,000.00
    Soft Costs
    2019-2020
    PRESIDIO NETWK. SOLUTIONS INC.
    $540.00
    Soft Costs
    2019-2020
    TERRACON CONSULTANTS, INC.
    $68,197.08
    Soft Costs
    2019-2020
    TEXAS DEPARTMENT OF STATE
    $387.00
    Technology
    2019-2020
    PIRAINO CONSULTING, INC.
    $197,910.62