Skip Navigation
 

Sam Houston HS LogoTotal Funds
$33,190,150

Total Spend to date
$8,255,723

Architect: KAI Texas
Contractor: Joeris
Project Status: Construction

The project scope includes upgrading entire infrastructure, replacing windows and roof, improving security, upgrading classrooms to SAISD standards and incorporating some 21st Century Learning

Renovations and upgrades to include:

  • Classroom spaces (general learning, science, special education)
  • Restrooms
  • Cafeteria/kitchen
  • Auditorium
  • Heating, ventilation and air conditioning
  • Plumbing and electrical
  • Technology infrastructure for new and renovated spaces
  • Lighting
  • Fire sprinkler systems
  • Special needs accessibility in entryways, restrooms, and other areas
  • Front-entry modifications to improve security
  • Athletic track re-coating
  • Tennis court fencing
  • Roofing, building exterior and site improvements

Latest Updates

Overall project completion currently scheduled for December 2020

May 2020: Library – Painting in progress, along with final cleaning and addressing punch list items to mark ending of the phases.

Work to the front classroom wing continued with overhead electrical work, while wall line connections are prepared. Workers are framing areas of the wall that have been expanded to include sheetrock coverup, duct and piping installation.

Front Entry, or Area B of the project, maintains a concrete slab that is currently in progress as of Spring 2020. 

Dining Area, or Area D of the project, includes ductwork in progress, ceiling cover up pending overhead inspection.

In the auditorium, the ceiling grid in the back of the house is in progress as of Spring 2020.

Around the Site: Temporary irrigation at softball field is complete, and excavation for new landscaping in front of school is in progress.

April 22, 2019: Stakeholder Meeting. Click here for the presentation.

September 29, 2018: A Community Meeting took place in the Cafeteria. Click here for the presentation.

March 21, 2018: A Project Advisory Team Meeting was held.

Sam Houston HS Summary Bond Expenditures
Budget Description Budget Committed Costs Cost to Date Uncommitted Costs
Construction $24,892,613 $24,892,613 $6,443,733 $0
Soft Costs $5,310,424 $2,784,623 $1,756,875 $2,525,801
FFE $995,705 $995,705
Technology $331,902 $118,850 $55,115 $213,051
Contingency $1,120,168 $1,120,168
Project Total $32,650,810 $28,335,425 $8,255,723 $4,854,725


Legend:

Construction:  New construction and renovation costs, contractor and design contingency
Soft Costs:  Architect design fees, Construction Manager fees, Design Consultants, QA/QC Services, fees, temporary facilities, abatement
Furniture, Fixtures & Equipment (FFE):  Classroom furniture, owner provided equipment
Technology:  Technology hardware & infrastructure
Contingency:  Owner's contingency, inflation, project reserves



  • Category
    School Year
    Vendor Name
    Total Expenditures
    Construction
    2018-2019
    JOERIS GENERAL CONTRACTORS LTD
    $881,924.32
    Construction
    2019-2020
    JOERIS GENERAL CONTRACTORS LTD
    $13,503,217.11
    Soft Costs
    2017-2018
    KAI-ALLIANCE LC
    $219,699.74
    Soft Costs
    2018-2019
    ALPHA TESTING INC.
    $11,300.00
    Soft Costs
    2018-2019
    AZTECA DESIGNS, INC.
    $41,380.44
    Soft Costs
    2018-2019
    GULF COAST PAPER CO INC
    $421.94
    Soft Costs
    2018-2019
    INDUSTRY1ONE STAFFING
    $2,843.08
    Soft Costs
    2018-2019
    INTELLIGENT ENGINEERING
    $12,230.00
    Soft Costs
    2018-2019
    JOERIS GENERAL CONTRACTORS LTD
    $47,399.85
    Soft Costs
    2018-2019
    KAI-ALLIANCE LC
    $779,832.20
    Soft Costs
    2018-2019
    RABA-KISTNER CONSULTANTS, INC.
    $4,700.00
    Soft Costs
    2018-2019
    TESSMAN ROAD LANDFILL
    $123.64
    Soft Costs
    2019-2020
    B & M LIMITED PARTNERSHIP
    $25,370.72
    Soft Costs
    2019-2020
    CLEARY ZIMMERMANN ENGINEERS
    $9,208.03
    Soft Costs
    2019-2020
    KAI-ALLIANCE LC
    $251,520.49
    Soft Costs
    2019-2020
    MCGRATH RENTCORP
    $2,100.00
    Soft Costs
    2019-2020
    PRESIDIO NETWK. SOLUTIONS INC.
    $56,765.23
    Soft Costs
    2019-2020
    PSI INC
    $6,337.00
    Soft Costs
    2019-2020
    TEXAS DEPARTMENT OF STATE
    $330.00
    Technology
    2019-2020
    INTEGRATED AV SYSTEMS LLC
    $32,796.00
    Technology
    2019-2020
    PIRAINO CONSULTING, INC.
    $191,939.06
    Page 1 of 1

Copyright © {{YEAR}} San Antonio Independent School District. All rights reserved.

powered by ezTaskTitanium TM