Skip Navigation
  • Burbank High School Schematic Design

  • Burbank High School Exterior construction

  • Burbank High School Second floor construction

  • Burbank High School Ongoing construction

  • Burbank High School Kitchen construction

  • Burbank High School Overhead shot

  • Burbank High School Ground breaking ceremony

  • Burbank High School Start of project

 

Latest Updates

Fall 2020:

Mechanical, electrical and plumbing trades are ongoing on all three floors as well concrete masonry units work. Exterior sheathing on north and south exterior walls is ongoing.

February-April 2020: Building pad excavation continued, with piers being drilled for the central plant. The masonry on the exterior part of the building began. 

January 2020: Picking up from the last part of 2019, foundations for the first, second and third floors were poured. 

October-December, 2019: Installed underfloor drainage system, as well as poured foundation for multiple sections of the new academic building. 

July, 2019: Completed site demolition and building pad excavation for new academic building to be constructed.

July 8, 2019: Groundbreaking ceremony held on the site of the new campus to thank the Burbank High School team helping create the new campus.

April 18, 2019: Stakeholder Meeting. Click here for the presentation.

September 20, 2018: A Community Meeting took place in the Cafeteria. Click here for the presentation.

April 26, 2018: As the design progresses, we will begin to incorporate Project Advisory Team meetings. The principal met with personnel from facilities and staff ahead of the PAT meeting.

Burbank Logo











Total Funds

$79,439,675

Total Spend to date
$9,593,874

Architect: Garza Bomberger & Associates
Contractor: Morganti/Casias
Project Status: Major Contsruction

Designing a new main building provides a great opportunity to give the students a campus to take pride in. Linking the existing campus with a newly designed building is an exciting part of the process. The design team reviewed the existing floor plans with the principal, Mr. Elizondo, and discussed programming needs, building flow and phasing.

Later, the auditorium will be targeted for renovation.

Copyright © {{YEAR}} San Antonio Independent School District. All rights reserved.

powered by ezTaskTitanium TM