Latest Updates
Fall 2020:
Mechanical, electrical and plumbing trades are ongoing on all three floors as well concrete masonry units work. Exterior sheathing on north and south exterior walls is ongoing.
February-April 2020: Building pad excavation continued, with piers being drilled for the central plant. The masonry on the exterior part of the building began.
January 2020: Picking up from the last part of 2019, foundations for the first, second and third floors were poured.
October-December, 2019: Installed underfloor drainage system, as well as poured foundation for multiple sections of the new academic building.
July, 2019: Completed site demolition and building pad excavation for new academic building to be constructed.
July 8, 2019: Groundbreaking ceremony held on the site of the new campus to thank the Burbank High School team helping create the new campus.
April 18, 2019: Stakeholder Meeting. Click here for the presentation.
September 20, 2018: A Community Meeting took place in the Cafeteria. Click here for the presentation.
April 26, 2018: As the design progresses, we will begin to incorporate Project Advisory Team meetings. The principal met with personnel from facilities and staff ahead of the PAT meeting.