Latest Updates

Fall 2020:

Fine Arts renovations and additions have been completed, as well as the Field House turned over to the campus by the construction company for the start of the 2020/21 school year.

Work in the other athletic facilities is ongoing, including electrical in wall and overhead ongoing at primary gym and door frame installation at primary gym. Field House fire sprinkler inspections are scheduled. Underfloor plumbing is ongoing at primary gym.

Spring 2020
-Secondary Gym is complete
-Primary Gym has had all the interior demolition and abatement completed
-Fine Arts, Dance Studio, and Blackbox theater are all nearing completion for the end of the month (ready for next school year)
-New Field House is under construction and will be ready for the football season

4.23.19: Stakeholder Meeting. Click here for the presentation.

9.26..18: A Community Meeting took place in the Cafeteria. Click here for the presentation.

A Project Advisory Team meeting will be scheduled soon. So far, the principal has met with Edison staff and construction services.

Edison Logo











Total Funds

$21,939,497

Total Spend to date
$15,086,704

Architect: PBK
Contractor: Bartlett Cocke
Project Status: Construction

Edison HS has a unique courtyard and canopy for outdoor use located between the fine arts building and, cafeteria, and the boy’s gym. Staff and architects will discuss the scope of work for the athletics department as well as the budget for Edison HS.

Renovations and upgrades to include:

  • Field House Replacement
  • Athletic facilities and support areas
  • Auditorium
  • Heating, ventilation and air conditioning
  • Plumbing and electrical
  • Technology infrastructure for new and renovated spaces
  • Lighting
  • Roof replacement
  • Fire sprinkler systems
  • Special needs accessibility in entryways, restrooms, and other areas
  • Front-entry modifications to improve security
  • Athletic track re-coating
  • Tennis court fencing
  • Roofing, building exterior and site improvements

Edison HS Summary Bond Expenditures
Budget Description Budget Committed Costs Cost to Date Uncommitted Costs
Construction $23,417,196 $23,416,293 $13,864,770 $903
Soft Costs $3,510,320 $1,434,335 $1,221,934 $2,075,985
FFE $658,185 $658,185
Technology $219,395 $219,395
Contingency $740,458 $740,458
Project Total $28,545,553 $25,207,145 $15,086,704 $3,694,925


Legend:

Construction:  New construction and renovation costs, contractor and design contingency
Soft Costs:  Architect design fees, Construction Manager fees, Design Consultants, QA/QC Services, fees, temporary facilities, abatement
Furniture, Fixtures & Equipment (FFE):  Classroom furniture, owner provided equipment
Technology:  Technology hardware & infrastructure
Contingency:  Owner's contingency, inflation, project reserves




  • Category
    School Year
    Vendor Name
    Total Expenditures
    Construction
    2018-2019
    AMSTAR INC.
    $2,985.00
    Construction
    2018-2019
    BARTLETT COCKE, L.P.
    $76,745.83
    Construction
    2019-2020
    BARTLETT COCKE, L.P.
    $9,592,151.76
    Soft Costs
    2017-2018
    CDS/MUERY SERVICES
    $63,485.50
    Soft Costs
    2017-2018
    PBK
    $104,486.86
    Soft Costs
    2018-2019
    ARIAS & ASSOCIATES INC.
    $12,800.00
    Soft Costs
    2018-2019
    CDS/MUERY SERVICES
    $13,600.00
    Soft Costs
    2018-2019
    GT GRANDSTANDS, INC
    $104,180.00
    Soft Costs
    2018-2019
    GULF COAST PAPER CO INC
    $399.80
    Soft Costs
    2018-2019
    HALFORD BUSBY, LLC
    $28,200.00
    Soft Costs
    2018-2019
    INDUSTRY1ONE STAFFING
    $2,069.41
    Soft Costs
    2018-2019
    LYNWOOD BLDG. MATERIALS, INC
    $35.04
    Soft Costs
    2018-2019
    MCGRATH RENTCORP
    $1,521.80
    Soft Costs
    2018-2019
    MOVE SOLUTIONS-SAN ANTONIO LTD
    $2,584.43
    Soft Costs
    2018-2019
    PBK
    $595,817.23
    Soft Costs
    2018-2019
    RENDON, AL
    $900.00
    Soft Costs
    2018-2019
    TERRACON CONSULTANTS, INC.
    $19,313.75
    Soft Costs
    2018-2019
    TESSMAN ROAD LANDFILL
    $238.39
    Soft Costs
    2019-2020
    ALAMO MUSIC CENTER, INC.
    $1,300.00
    Soft Costs
    2019-2020
    FUGRO CONSULTANTS, INC
    $18,908.75
    Soft Costs
    2019-2020
    MCGRATH RENTCORP
    $3,534.60
    Soft Costs
    2019-2020
    PBK ARCHITECTS, INC.
    $296,870.52
    Soft Costs
    2019-2020
    TERRACON CONSULTANTS, INC.
    $23,216.50
    Technology
    2019-2020
    PIRAINO CONSULTING, INC.
    $34,971.48