Fox Tech High School

Bond 2020 Program Phase 2 School

Current Status: Construction Documents

Planned Scope of Work*

  • Construct new performing arts building
  • Renovate black box theater in music building
  • Renovate competition and secondary gyms

*Project scope has been modified from original planned scope

Update 

Bids have been submitted for renovations to Fox Tech High School, and a recommended Guaranteed Maximum Price (GMP) for long-lead items (mechanical and electrical) is expected to go to the Board of Trustees for approval in July 2024.

Included in the construction plans are a new performing arts building that includes an auditorium, a scene shop, and educational spaces for visual arts. A new black box theater will be built as a standalone building.

Also planned is a full remodel of the competition and secondary gyms, to include flooring, bleachers, basketball goals, windows, paint, and HVAC systems. The two gyms will be adjoined by new athletic facilities that house boys and girls locker rooms, coaches offices, and a laundry facility. 

Updated4/18/24

Renderings are conceptual and may differ from final design.
Fox Tech HS logo

Project Team
General Contractor:  
Bartlett Cocke

Architect:  
Alta Architects, Inc.

SAISD Project Manager:  
Patrick Cooper
Construction & Development Services Dept.

Trustee District #1:  
Sarah Sorensen

Total Project Budget**
$78,871,204

**The total project budget, which includes architectural, engineering, and construction costs, may differ from the original budget due to program modifications necessitated by the rising cost of construction, the implementation of strategic district initiatives, or other program impacts