Washington Irving Dual Language Academy

Bond 2020 Program Phase 2 School

Current Status: Under Construction

Planned Scope of Work* 

  • Build new weight room
  • Build new gymnasium with locker room, showers, and restrooms
  • Renovate secondary gymnasium
  • Make exterior improvements/outdoor learning space

*Project scope has been modified from original planned scope

Update

Construction is underway at Irving Dual Language Academy. As of February 2024, the competition gym and old classroom wing had been demolished to make way for the new competition gym, weight room and locker rooms. Still to come is the renovation of the secondary gym, and exterior improvements, including the addition of an outdoor learning space.

All Bond 2020 renovations at the school are expected to be completed in summer 2025.

 

Updated 4/17/24

Renderings are conceptual and may differ from final design.
Irving Academy logo

Project Team
General Contractor:  
Bartlett Cocke

Architect:  
O’Connell Robertson

SAISD Project Manager:  
Carolina Hurtado
Construction & Development Services Dept.

Trustee District #5:  
Stephanie Torres

Total Project Budget**
$9,734,799

 

**The total project budget, which includes architectural, engineering, and construction costs, may differ from the original budget due to program modifications necessitated by the rising cost of construction, the implementation of strategic district initiatives, or other program impacts